The service of RealVCE
Update Our Company checks the update every day. If you've bought Construction-Manager real dumps from us, once there is Construction-Manager vce dumps released, our system will send it to your e-mail immediately. And you can free update the Certified Construction Manager (CCM) vce dumps one-year after you purchase.
Refund We promise to you full refund if you failed the exam with Certified Construction Manager (CCM) real vce. Within 7 days after exam transcripts come out, then scanning the transcripts, add it to the emails as attachments and sent to us. After confirmation, we will refund immediately.
Payment Our payment is by Credit Card. But it can be bound with the credit card, so the credit card is also available.
Instant Download: Our system will send you the Construction-Manager braindumps file you purchase in mailbox in a minute after payment. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
One day when you find there is no breakthrough or improvement in your work and you can get nothing from your present company. May be changing yourself and getting an important certificate are new start to you. As people who want to make a remarkable move in IT field, getting Construction-Manager certification will make a big difference in their career. But the matter now is how to pass Certified Construction Manager (CCM) real exams quickly and high-effectively. It is known that the high-quality and difficulty of Certified Construction Manager (CCM) real questions make most candidates failed. Most candidates have no much time to preparing the Certified Construction Manager (CCM) vce dumps and practice Certified Construction Manager (CCM) real questions. Now, RealVCE will be your partner to help you pass the Certified Construction Manager (CCM) real exams easily. You just spend your spare time to review Certified Construction Manager (CCM) real dumps and Certified Construction Manager (CCM) pdf vce, you will pass real test easily.
You may wonder how I can ensure you pass Construction-Manager real test quickly. I will tell you reasons. First, we are specialized in the study of Certified Construction Manager (CCM) real vce for many years and there are a team of IT elites support us by creating Certified Construction Manager (CCM) real questions and Construction-Manager vce dumps. Our IT workers have rich experience in the pass guide of Certified Construction Manager (CCM) real exams. If you pay much attention to Certified Construction Manager (CCM) real dumps, I believe you can 100% pass Certified Construction Manager (CCM) real test.
Besides, for your convenience, RealVCE create online test engine, which you can only enjoy from our website. Most IT workers prefer to choose online test engine version to prepare their Construction-Manager real exams because it can support any electronic equipment and you can feel the atmosphere of Construction-Manager real test. When you begin to practice Certified Construction Manager (CCM) real questions you can set your test time like in real test. Besides, the online version will remark your problems and remind you to practice next time.
You should know that our pass rate is up to 89% now according to the date of recent years and the comment of our customer. Many of our returned customer said that our Certified Construction Manager (CCM) real questions have 85% similarity to the real test. Now, more than 100000+ candidates joined us and close to their success.
CMAA Construction-Manager Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Sustainability | 5% | - Green Building Practices
|
| Topic 2: Quality Management | 10% | - Quality Assurance and Control
|
| Topic 3: Time Management | 10% | - Delay Analysis
|
| Topic 4: Technology | 5% | - Information Management
|
| Topic 5: Cost Management | 10% | - Budget Development and Control
|
| Topic 6: Risk Management | 10% | - Risk Identification and Assessment
|
| Topic 7: Professional Practice | 10% | - Leadership and Communication
|
| Topic 8: Safety Management | 10% | - Incident Management
|
| Topic 9: Program & Project Management | 20% | - Resource Management
|
| Topic 10: Contract Administration | 10% | - Claims and Disputes
|
CMAA Certified Construction Manager (CCM) Sample Questions:
1. Under the Brooks Act, professional services of architects and engineers on federal projects must be
A) funded by public dollars.
B) contracted before GC services.
C) qualification-based rather than bid.
D) audited every six months.
2. During the design phase of a project, the owner had requested the design team develop mitigating strategies due to expected budget concerns. During the procurement process, the agency CM should advise the owner consider
A) incorporating Time and Material Alternates into the bid documents.
B) evaluating Phase Alternates in the bid documents.
C) incorporating Add/Deduct Alternates into the bid documents.
D) evaluating Schedule Alternates in the bid documents.
3. A dispute arises during construction after the contractor encounters what they feel is unsuitable material. The CM is not notified about the areas of concern, and the contractor hauls 10.000 cy of material offsite. Three months later, the contractor submits a claim for additional cost to haul the material off. The CM should advise the owner that
A) the owner should pay for the haul.
B) the claim is not valid because the contractor failed to provide timely notice.
C) the owner should pay the claim due to lack of owner information.
D) the owner should pay 50% of the haul since the contractor did not notify the CM first.
4. A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month
10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million.
Which statement most accurately portrays program status?
A) Behind schedule, pay application accurately reflects percentage complete.
B) On schedule, pay application accurately reflects percentage complete.
C) On schedule, pay application exceeds percentage complete.
D) Behind schedule, pay application exceeds percentage complete.
5. As the owner's representative, you are providing on-site construction management services to a municipality for their new design-build city hall project.
The mechanical subcontractor discovers that his ductwork will not fit in the above-ceiling area of the Mayor's office. Which entity is best-suited to resolve this risk?
A) Owner (Municipality)
B) Architect (DOR)
C) Design-Build Team
D) Owner's rep
Solutions:
| Question # 1 Answer: C | Question # 2 Answer: C | Question # 3 Answer: B | Question # 4 Answer: A | Question # 5 Answer: C |