Updated Sep-2021 Exam Engine or PDF for the SAP C_TS422_2020 test to help you quickly prepare for the SAP exam! [Q35-Q54]

Share

Updated Sep-2021 Test Engine or PDF for the SAP C_TS422_2020 test to help you quickly prepare for the SAP exam!

Full C_TS422_2020 Practice Test and 82 unique questions with explanations waiting just for you, get it now!

NEW QUESTION 35
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers tothis question.

  • A. Add the agreement to the source list and mark itfor MRP relevance.
  • B. Add the agreement to the quota arrangement and mark it for MRP relevance.
  • C. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
  • D. Set the creation indicator for purchase requisitions on the initial screen of the MRP run.

Answer: A,C

 

NEW QUESTION 36
Which master data object governs the relationship between supply source and demand source in the Kanban process?

  • A. Control cycle
  • B. Production supply area
  • C. Rate routing
  • D. Replenishment strategy

Answer: A

 

NEW QUESTION 37
When can the material availability check occur automatically in a production order? Note: There are 2 correct answers to this question.

  • A. At order release
  • B. At order confirmation
  • C. At order creation
  • D. At order settlement

Answer: A,C

 

NEW QUESTION 38
You want to perform capacity availability checks on your production orders. What must be set for this to occur? Note: Thereare 2 correct answers to this question.

  • A. Checking control must have an overall profile assigned in customizing.
  • B. Indicator Relevant for finite scheduling must be set.
  • C. PRT Availability check must be set.
  • D. Checking rule and group must be assigned.

Answer: A,B

 

NEW QUESTION 39
When working with both cross-plant and plant-specific material statuses in the mater al master, which status has the highest priority?

  • A. The plant-specific status
  • B. The least restrictive status
  • C. The cross-plant status
  • D. The most restrictive status

Answer: D

 

NEW QUESTION 40
What are some uses for the low-level code assigned to each material? Note: There are 2correct answers to this question.

  • A. It is used by ATP to determine the priority of alternative components.
  • B. It is used in MRP to determine the sequence in which materials are planned.
  • C. It is used by engineering to identify sub items in an engineering bill of material(BOM).
  • D. It is used by product costing to determine how costs are rolled up.

Answer: B,D

 

NEW QUESTION 41
How would you define pegging in the context of Advanced Planning?

  • A. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run.
  • B. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements.
  • C. An evaluation that is ordered according to thebill-of-material structure of all related products and represents the relationship between the receipt and the issue elements.
  • D. An evaluation to verify if there are mater al or capacity shortages in the network after the production planning run.

Answer: C

 

NEW QUESTION 42
If the stock level drops below the reorder stock in reorder point planning, what is the system logic to trigger procurement?

  • A. Fill up based on the lot size procedure
  • B. Fill up to the safety stock level
  • C. Fill up to the reorder stock level
  • D. Fill up to the maximum stock level

Answer: A

 

NEW QUESTION 43
Advanced Planning uses master data and transaction data from SAP S/4HANA In which data obje can you set the advanced planning flag? Note: There are 2 correct answers to this question.

  • A. Material
  • B. Plant
  • C. Production version
  • D. Work center

Answer: A,D

 

NEW QUESTION 44
Which materials have a negative quantity in a bill of materials or in a recipe? Note: There are 3 correct answers to this question.

  • A. Continuous flow materials
  • B. Co-products
  • C. Waste products
  • D. By-products
  • E. Bulk materials

Answer: B,C,D

 

NEW QUESTION 45
What is the purpose of a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.

  • A. To determine the work in progress along the production line
  • B. To provide timely updates of inventory management for the staged components
  • C. To stage different components for a production line simultaneously
  • D. To reduce the totalproduction lead time for along production line

Answer: A,B

 

NEW QUESTION 46
Where do you maintain the duration of a producton operation?

  • A. Material master
  • B. Routing
  • C. Bill of material (BOM)
  • D. Work instructions

Answer: B

 

NEW QUESTION 47
Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?

  • A. Use batch determination.
  • B. Use the material where-used report.
  • C. Use the material staging report.
  • D. Use the batch information cockpit.

Answer: D

 

NEW QUESTION 48
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.

  • A. The planning strategy is infinite.
  • B. The work center has several individual capacities.
  • C. The Change Planning Direct on indicator is set.
  • D. Alternative resources are fully occupied.

Answer: A,B

 

NEW QUESTION 49
In your plant, MRP is activated. Which options do you have to exclude a material from the MRP run?Note:
There are 2 correct answers to this question.

  • A. Use a specific material group
  • B. Use a specific MRP type.
  • C. Use a specific material status.
  • D. Use a specific MRP controller.

Answer: B,D

 

NEW QUESTION 50
Which SAP solutions support the supplier area in the portfolio of the Digital Value Network? Note: There are
3 correct answers to this question.

  • A. SAP Concur
  • B. SAP Ariba
  • C. SAP C/4HANA
  • D. SAP Field glass
  • E. SAP SuccessFactors

Answer: A,B,D

 

NEW QUESTION 51
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.

  • A. Work Center BOM
  • B. Sales Order BOM
  • C. Functional Location BOM
  • D. Class BOM

Answer: B,C

 

NEW QUESTION 52
What determines whether the planned independent requirements in MRP consume other requirements?

  • A. Requirements type
  • B. Consumption sequence procedure
  • C. Requirements profile
  • D. Order type

Answer: A

 

NEW QUESTION 53
You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?

  • A. Manual planning without check
  • B. Consumption-based planning
  • C. Forecast planning
  • D. Material requirements planning

Answer: B

 

NEW QUESTION 54
......

Get Latest C_TS422_2020 Dumps Exam Questions: https://drive.google.com/open?id=1LB2v7d0rCKHS03F6oPUQoQfv0spM7YFA

Full C_TS422_2020 Practice Test and 82 unique questions with explanations waiting just for you, get it now: https://www.realvce.com/C_TS422_2020_free-dumps.html