NEW QUESTION 43
Your customer has a signed NDA that is stored within Ariba Contract Management. Now the customer wants to create an agreement for services ... What should the customer do to create the new contract workspace?
- A. Create a sub-agreement
- B. Create a sub-project
- C. Copy the NDA workspace
- D. Create a follow-on project
Answer: B
Explanation:
https://help.sap.com/viewer/16271706b2114c81ae784e5eb7b81ef0/cloud/en-US/6af298d4c1da10149a53d558025884d8.html
NEW QUESTION 44
When you create a Sub-agreement, which of the following hierarchy types are required for a Parent Agreement?
- A. Master Agreement, Stand alone Agreement. or Sub-Agreement
- B. Stand alone Agreement or Master Agreement
- C. Stand alone Agreement or Sub-Agreement
- D. Master Agreement or Sub-Agreement
Answer: D
Explanation:
https://help.sap.com/viewer/93d751e10a9042bebb776fc42aba0ea1/11.0/pt-
BR/9dca378dba1a404d909d14712b9a6aac.html
NEW QUESTION 45
Which task attributes does your customer need to review while designing the contracting process?
Note: There are 3 correct answers to this question
- A. Task End Dates
- B. Task Description (Missed)
- C. Access Control
- D. Required or Optional (Missed)
- E. Conditions (Missed)
Answer: B,D,E
NEW QUESTION 46
Which amendment type do you use if your customer only needs to change the team members?
- A. Renewal amendment
- B. Termination amendment
- C. Administrative amendment
- D. Amendment amendment
Answer: A
Explanation:
https://www.contractexperience.com/resources/contract-amendment.html
NEW QUESTION 47
What is the purpose of the Notice Date attribute field?
- A. The date when the project owner will receive notice to review a contract with a perpetual term
- B. The date that is used for a reminder about a deliverable due date
- C. The date when one of the parties has to provide notice to the other about any changes to the termination status of ...
- D. The date to delete the contract record according to the corporate policy for document retention
Answer: B
Explanation:
https://help.sap.com/viewer/7a107e5958ff44d8b5e671be81ce4551/cloud/en-
US/7be2781771ea1014871c84a8eda24442.html
NEW QUESTION 48
Which of the following fields does Ariba Contract Management deliver as out-of-the-box fields? Note:
There are 2 correct answers to this question
- A. Departments
- B. Contract Locations (Missed)
- C. Agreement Type (Missed)
- D. Regions
Answer: A,D
Explanation:
https://support.ariba.com/item/view/142951
NEW QUESTION 49
Why do you use Team Member Rules files?
- A. To set access rights and permissions for team members who have previously been added to a project
- B. To assign custom groups to project teams based on project metadata
- C. To add site-wide permissions to the team members
- D. To restrict the approval rules that are assigned to team members at the task level
Answer: D
Explanation:
https://help.sap.com/viewer/707c28a3723e4ba49d67279b9f1a3539/cloud/en-
US/7da367c071ea10149a0ff615f9058b06.html#:~:text=Team%20member%20rules%20files%20help,ass ociated%20with%20different%20commodity%20categories.
NEW QUESTION 50
What must you check when you import templates from one Contract Management realm to another?
Note: There are 2 correct answers to this question
- A. The Contract Management solution must be of the same version and service pack (Missed)
- B. The documents must all be published
- C. The Process template must be in Published status
- D. Both instances must share the same master data (Missed)
Answer: A,D
NEW QUESTION 51
What Ariba document types can be stored on the Documents tab in a contract workspace? Note: There are 2 correct answers to this question
- A. Supplier Performance Management projects
- B. Analytical reports (Missed)
- C. Supplier profile questionnaire (Missed)
- D. Sourcing surveys
Answer: A,C
Explanation:
https://support.ariba.com/Item/view/184871/1/1C66B8X
NEW QUESTION 52
What actions can you perform in the Outline view? Note: There are 2 correct answers to this question
- A. Redline and track changes of negotiated documents
- B. Drag and drop sections and clauses (Missed)
- C. Access the clause library to add and substitute clauses (Missed)
- D. Make changes to bookmarks and styles
Answer: B,D
Explanation:
https://www.uwec.edu/kb/article/microsoft-word-2007-using-the-outline-
view/#:~:text=About%20Outline%20View,view%20is%20indicated%20by%20symbols.
NEW QUESTION 53
Under which conditions are you NOT able to view the History tab in a contract workspace? Note: There are 2 correct answers to this question
- A. The contract is in draft status
- B. You are viewing the workspace in Compact view (Missed)
- C. You do NOT have classified access
- D. You are NOT part of the project owner group (Missed)
Answer: C,D
NEW QUESTION 54
From where can you create a contract workspace? Note: There are 3 correct answers to this question
- A. From a contract request (Missed)
- B. From an awarded sourcing event (Missed)
- C. From a Sourcing Project template
- D. From the dashboard (Missed)
- E. From a contract analytical report
Answer: A,C,E
NEW QUESTION 55
You are setting up a number of contracts with different suppliers to work on a facilities construction project. How would you create the new workspaces to link them to each other in the system?
- A. Create a sub-project
- B. Create follow-on projects
- C. Create sub-agreements
- D. Copy the project
Answer: B
NEW QUESTION 56
Which view option displays contract search results in a hierarchy?
- A. List
- B. Details
- C. Hierarchical
- D. Tree
Answer: D
NEW QUESTION 57
What are the benefits of Template tasks? Note: There are 2 correct answers to this question
- A. You can add owners and observers to simplify the end-user process (Missed)
- B. You can create and manage notification profiles on the projects level
- C. They are used to standardize business processes
- D. End users can choose which template tasks required for their projects (Missed)
Answer: C,D
NEW QUESTION 58
What factor determines whether a supplier can respond to a negotiation task by directly accessing the contract workspace?
- A. Supplier user is a member of the supplier's legal team
- B. Supplier user is an e-mail reviewer
- C. Supplier user is registered on the Ariba Network
- D. Supplier user is a contract manager
Answer: A
NEW QUESTION 59
Which of the following are attributes of Partial Bookmarking? Note: There are 2 correct answers to this question
- A. Any content that is NOT bookmarked is treated as a separate clause (Missed)
- B. The section GlobalContract bookmark tag is necessary
- C. Section bookmarks are NOT required
- D. All properly entered bookmarks are respected (Missed)
Answer: A,B
Explanation:
https://help.sap.com/viewer/7927b70bbc0b4f63ad54bba16edad608/cloud/en-
US/7bebef0e71ea101490a9a1c5552db5aa.html
NEW QUESTION 60
What best practice does SAP Ariba recommend for tasks related to a contract amendment? Note: There are 2 correct answers to this question
- A. Apply visibility conditions that are based on the amendment type selected by the user
- B. Configure the notification profile to send an e-mail to the project team when the tasks are complete
- C. Create a predecessor task to prevent the tasks from starting early (Missed)
- D. Enable the Repeat for each Document Draft option (Missed)
Answer: A,C
NEW QUESTION 61
Fields from which locations can be used as document properties in assembled documents? Note: There are 2 correct answers to this question
- A. Supplier Profile Questionnaire
- B. Sourcing Project Header
- C. Form Header (Missed)
- D. Contract Workspace Header (Missed)
Answer: A,B
NEW QUESTION 62
What does SAP Ariba recommend when populating the enablement workbook?
- A. You must modify the Reference - System Level Codes worksheet to add currencies NOT specified in the workbook
- B. You must save each worksheet as a separate csv file for the import
- C. You may NOT delete the unused worksheets
- D. You may NOT modify worksheet names
Answer: D
Explanation:
https://help.sap.com/viewer/b6d46a2e6c3043d7bb0cbabba4262560/cloud/en-US/7dcfed9971ea1014a815bb787179d5b0.html
NEW QUESTION 63
What benefit does your customer have by using the contract template? Note: There are 2 correct answers to this question
- A. Template items can be deleted in projects
- B. New header fields can be created
- C. Workspace content can be re-used (Missed)
- D. Standardized workflow is applied to all workspaces (Missed)
Answer: C,D
NEW QUESTION 64
What options are available if you need to involve suppliers in a customer's contracting process? Note:
There are 2 correct answers to this question
- A. Initiate the contract from a sourcing event awarded to the supplier (Missed)
- B. Invite the supplier to a survey to collect their feedback on the draft agreement
- C. Create an external user account and assign it to the Team tab of a contract workspace (Missed)
- D. Add a supplier contact as an e-mail reviewer for Negotiation task
Answer: B,C
NEW QUESTION 65
What are the characteristics of a best-practice process workflow? Note: There are 2 correct answers to this question
- A. Ensures that only the project owner starts any of the tasks
- B. Enforces required tasks to map out a standardized repeatable processes (Missed)
- C. Contains a 20-task step-by-step workflow built mostly from To-Do tasks
- D. Focuses on milestones, reviews, and approvals (Missed)
Answer: B,D
Explanation:
https://www.mindtools.com/pages/article/newTMC_97.htm
NEW QUESTION 66
......
Focus on C-ARCON-2102 All-in-One Exam Guide For Quick Preparation: https://www.realvce.com/C-ARCON-2102_free-dumps.html