NEW QUESTION 43
Which of these may a Development Team deliver at the end of a Sprint (choose 2)?
- A. An increment of software with minor known bugs in it
- B. A single document, if that is what the Product Owner asked for
- C. Failing unit tests, to identify acceptance tests for the next Sprint
- D. An increment of working software that is "done."
Answer: B,D
NEW QUESTION 44
What is the maximum duration of each Sprint planning meeting section?
- A. 4 hours
- B. 2 hours
- C. 15 minutes
- D. 1 hour
- E. 30 minutes
Answer: A
NEW QUESTION 45
Which of the following statements best explains what the term Sprint means in Scrum?
- A. A sprint is a specific amount of days for a team to test and resolve any issues prior to product release or shipment
- B. A sprint is a specific amount of days for a team to work as many hours as needed to finish assigned work
- C. A sprint is a specific amount of days for a team to work at a sustainable pace to finish select work.
- D. A sprint is an agreed upon period of time for team members to select individual items from the product backlog to work on.
Answer: C
NEW QUESTION 46
The individual, detailed pieces of work that are needed to convert a product backlog item into a working
software component or solution are called:
- A. Line items
- B. Tasks
- C. Use cases
- D. User Stories
Answer: B
NEW QUESTION 47
Who acts as a facilitator between Product Owner and Team in a project?
- A. Process Owner
- B. Stakeholder
- C. ScrumMaster
- D. Developer
Answer: C
NEW QUESTION 48
What happens when all committed items (requirements) are not completed at the end of the Sprint?
- A. The Sprint duration is extended
- B. The tasks are determined to be unnecessary
- C. None of the above
- D. They return to the product backlog
Answer: D
NEW QUESTION 49
Which of the following statements best explains what the term Sprint means in Scrum?
- A. A sprint is a specific amount of days for a team to test and resolve any issues prior to product release orshipment
- B. A sprint is a specific amount of days for a team to work as many hours as needed to finish assigned work
- C. A sprint is a specific amount of days for a team to work at a sustainable pace to finish select work.
- D. A sprint is an agreed upon period of time for team members to select individual items from the productbacklog to work on.
Answer: C
NEW QUESTION 50
The Product Backlog is maintained by:
- A. The Development Team
- B. The Product Owner and Scrum Master
- C. The Scrum Master
- D. The Product Owner
Answer: D
NEW QUESTION 51
Which of the following are valid Scrum Meetings? (Choose four.)
- A. Sprint Planning Meeting
- B. Sprint Review Meeting
- C. Sprint Retrospective Meeting
- D. Audit Meeting
- E. Daily Scrum
- F. Agile Development Meeting
- G. Business Analysis Meeting
Answer: A,B,C,E
Explanation:
Explanation/Reference: https://www.ntaskmanager.com/blog/scrum-meetings/
NEW QUESTION 52
In an Agile environment, planning happens at which two levels? (Choose two.)
- A. release planning
- B. sprint planning
- C. product planning
- D. backlog planning
Answer: A,B
NEW QUESTION 53
Which of the following is not a Scrum Master responsibility?
- A. Establish priorities together with product owner for Product Backlog items
- B. Empowering the team
- C. Socializing scrum throughout the organization
- D. Preventing Senior Management from shifting team priorities
Answer: D
NEW QUESTION 54
Who is required to attend the Daily Scrum?
- A. Development Team
- B. Development Team and Product Owner
- C. Development Team and Scrum Master
- D. Scrum Master
Answer: A
NEW QUESTION 55
Select which option best completes the following statement. __________ is all about response to change.
- A. Change management
- B. Customer satisfaction
- C. Agile
- D. Planning
Answer: C
NEW QUESTION 56
Which topics should be discussed in the Sprint Review?
- A. the process
- B. Sprint results
- C. coding practices
- D. all of the above
Answer: B
NEW QUESTION 57
Agile software development also promotes industry best practices that _______________ and
- A. Emphasize team members; partner involvement
- B. Emphasize managers; stakeholder involvement
- C. Emphasize teamwork; customer involvement
- D. Emphasize software developers; manager involvement
Answer: C
NEW QUESTION 58
________________ constitute the Sprint Backlog and are often estimated in hours?
- A. Features
- B. Tasks
- C. Use Cases
- D. User Stories
Answer: B
NEW QUESTION 59
Which of the following is not a Scrum artifact?
- A. Incremento de Software
- B. Product Backlog
- C. Sprint Backlog
- D. User Stories
Answer: D
NEW QUESTION 60
What is the Release Burn down?
- A. The work remaining to be completed by the Product Owner
- B. A measure of the remaining Product Backlog across the time of a release plan
- C. What has been completed by the Scrum Team to date
- D. A graph indicating what has been completed by the Scrum Team
Answer: B
Explanation:
Explanation/Reference:
NEW QUESTION 61
......