Hearing that an exam is difficult is not a reason to skip it; it is a reason to prepare properly. The CIMA Risk Management package at RealVCE gives you 223 practice questions for the CIMAPRA19-P03-1 exam in 2026's current format, and a free demo lets you gauge the difficulty honestly before spending a cent.
CIMA CIMAPRA19-P03-1 Exam Overview:
| Certification Vendor: | CIMA |
|---|---|
| Exam Name: | P3 Risk Management (Online) |
| Exam Number: | CIMAPRA19-P03-1 |
| Exam Price: | Approximately £95–£120 (varies by region and tax) |
| Exam Format: | Fill-in-the-blank (number entry), Multiple Response, Drag and drop, Multiple Choice |
| Available Languages: | English |
| Real Exam Qty: | 60 |
| Passing Score: | 100/150 (scaled score, approx. 67%) |
| Exam Duration: | 90 minutes |
| Related Certifications: | CIMA Strategic Level CIMA Operational Level CIMA Certificate in Business Accounting CIMA Management Level |
| Certificate Validity Period: | 3 years (as part of CIMA exam progression validity rules) |
| Recommended Training: | LearnSignal CIMA P3 Risk Management CIMA Official Learning |
| Exam Registration: | Pearson VUE CIMA Exams CIMA Exam Booking Portal |
| Sample Questions: | ![]() |
| Exam Way: | Computer-based exam (Pearson VUE test centres or online proctored exam) |
| Pre Condition: | Completion of CIMA Operational Level (or equivalent exemptions where applicable) |
| Official Syllabus URL: | https://www.aicpa-cima.com/cimaexams |
CIMA CIMAPRA19-P03-1 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Internal Controls | 25% | - Control Evaluation
|
| Strategic Risk | 25% | - External Environment Risk
|
| Enterprise Risk | 25% | - Risk Identification
|
| Cyber Risk | 25% | - Cyber Threats
|
CIMAPRA19-P03-1 Exam Basics: What Every Candidate Asks
The CIMAPRA19-P03-1 exam is the required test for earning the CIMA Risk Management certification from CIMA. It assesses your command of the official exam objectives through scenario-based and knowledge questions, and the resulting credential is widely recognized by employers. Its reputation for difficulty is real but manageable — candidates who practice consistently with quality materials routinely walk in well prepared.
The official outline for the CIMAPRA19-P03-1 exam highlights these domains:
- Cyber Risk (25%)
- Enterprise Risk (25%)
- Internal Controls (25%)
Seeing the topics laid out this way often shrinks the exam's intimidation factor — each domain is a finite, learnable block, and the CIMA Risk Management practice questions at RealVCE follow the same structure.
Completion of CIMA Operational Level (or equivalent exemptions where applicable)
The CIMAPRA19-P03-1 exam is demanding, but its difficulty is specific, not mysterious: unfamiliar question formats, time pressure, and a few heavily weighted domains. All three respond to the same remedy — repeated, timed exposure to exam-style questions. That is what the CIMA Risk Management practice materials at RealVCE provide, and the free demo lets you measure the real difficulty yourself before committing, which is usually the moment the fear starts shrinking.
The CIMAPRA19-P03-1 exam consists of 60 questions with a time allowance of 90 minutes minutes. Practicing full sets under a similar time cap is the most direct way to make sure pacing never costs you points on exam day.
CIMA offers these training resources for candidates:
Official courses explain the material; practice questions teach you how the exam asks about it. Most successful candidates use both.
Because seeing beats guessing. The free demo of the CIMAPRA19-P03-1 exam materials at RealVCE contains genuine samples from the full CIMA Risk Management question set — same format, same expert-verified answers — and downloading it costs nothing. If you are unsure whether the materials match your level or your study style, the demo answers that question with evidence rather than marketing, and every demo on the site is free of charge.
The passing score is 100/150 (scaled score, approx. 67%) and the exam fee is Approximately £95–£120 (varies by region and tax). Knowing both numbers early helps you plan: aim to be consistently above the passing mark in timed practice sessions before you spend the fee on a booking.
Registration is available through the following official channels:
Many candidates find that booking a date early converts vague anxiety into a focused countdown — a useful psychological trick while working through the CIMA Risk Management practice questions.
CIMA Risk Management Sample Questions:
GUJ A small but rapidly expanding company has recently opened several branches in locations far away from the Head Office. All of the branches are relatively small with no one branch accounting for more than 5% of turnover. Management has decided that the company is not yet large enough to install an Internal Audit function but is, nonetheless, concerned about maintaining adequate control and monitoring at the branches whilst allowing Branch Managers the opportunity to react to local circumstances as appropriate.
Which of the following measures would assist Head Office management in maintaining appropriate monitoring and control at the branches?
- A. Restricting the autonomy of individual Branch Managers to purely routine matters and instructing them to refer everything else to Head Office.
- B. Dealing with all Human Resource, recruitment, and similar issues directly from Head Office.
- C. Arranging visits by senior management to each branch periodically.
- D. Establishing an open communication policy for employees at branches to allow them to contact Head Office on any matter that concerns them.
- E. Instituting the use of a formalised budgetary control system at head office for all branches.
Correct Answer: C,D,E 🗳️
TDC is a company which runs gas-fired power stations in western Europe. The Risk Committee has just received a report that a power station built to the same design and specification in a developing country has recently collapsed. The causes of the collapse are unclear but the consequences for TDC would be catastrophic if something similar were to happen in Europe Which of the following actions being considered by the Risk Committee are ethical?
Select ALL that apply
- A. Send experts employed by TDC to the site of the collapse so that they can gather information first hand on what happened
- B. Decide that the information available to date is too uncertain to take any action for now
- C. Issue a press release confirming that all TDC's power stations are "entirely safe'.
- D. Commission a reputable firm of structural engineers to carry out a review of all power stations owned by TDC
- E. Draw up contingency plans in case some of TDC's power stations need to be shut down
- F. Attempt to increase the level of insurance cover against this type of eventuality
Correct Answer: A,D,E 🗳️
A project has an NPV of £1,200,000. The present value of material costs which are included in the NPV calculation are £8,000,000.
What is the sensitivity of the project to changes in material costs?
Give your answer to the nearest whole percentage.
Correct Answer:
15%
P Ltd, a manufacturing company, is considering a new capital investment project to set up a new production line. The initial appraisal shows a healthy net present value of $6,465 million at a discount rate of 10% as shown in the table below:
However, management is unsure about the demand for the product which will be produced and has insisted that the future revenues should be reduced to certainity equivalents by taking 70%, 65% and 60% of the years 1,2, and 3 cash inflows respectively.
What should P do?
- A. Stop the project, it has considerable risk.
- B. Proceed with the project, it has a healthy net present value.
- C. Re-appraise the project using other capital appraisal techniques to get a more balanced view.
- D. Put pressure on sales and marketing to re-verify their forecasts.
Correct Answer: C 🗳️
Which TWO of the following are NOT methods used for risk identification?
- A. Designing a process to deal with complaints
- B. Accounting for waste in a manufacturing process
- C. Carrying out interviews on key members of staff
- D. Employing external advisors with specialist knowledge
- E. Brainstorming ideas with colleagues from different disciplines within the business
Correct Answer: A,E 🗳️